Aug 222013
 

Start time : 9.30 – 10.00

Work Site: Society’s Barn at Colt Hill

Tasks will include:

At the barn

  • completing the top row of bricks in the corner
  • replace missing and broken tiles
  • fix outside woodwork (wall)
  • rake earth away from wall by electrical earth point and fill with shingle or concrete
  • fix the 2 new rafters to the adjacent woodwork
  • fix remainder of guttering

Lock 27

  • woodwork
  • level scalpings and wackerplate
  • sort out top soil level
  • (and bag up rubble at Lock 28 and bring it back to the barn for backfill)

Please let me know if you can come.

Janet

 